[Date Prev][Date Next][Thread Prev][Thread Next][Date Index
][Thread Index
]
BKK Post. February 25, 1998 ENERGY
- Subject: BKK Post. February 25, 1998 ENERGY
- From: burma@xxxxxxxxxx
- Date: Wed, 25 Feb 1998 04:31:00
February 25, 1998
ENERGY / ALL MAY NOT BE AS IT SEEMS
It's time to look again at the controversial Burma gas pipeline
Pibhop Dhongchai
Between February 14 and 18 Thais learnt a few truths about the Yadana
pipeline project through the national committee tasked with looking into
this controversial mega scheme.
The committee was chaired by former prime minister Anand Panyarachun and
composed of several well-respected members of society.
It seems the conservationists have fulfilled, to a certain degree, their
mission to push forward the issue and "enlighten" the public. At the
moment, all are waiting for Prime Minister Chuan Leekpai to decide
whether to bless or bust the project.
While some view the conservationists' proposals as too demanding, we
find several questions raised during the public hearing still
unanswered. To reiterate the conservationists' statement on the last day
of the meeting: as long as state agencies fail to provide truthful and
straightforward responses, the Thai-Burmese pipeline project should not
be allowed to continue.
Below are listed some key reasons as to why the project needs drastic
amendments:
1. The claim that any failure to meet the July 1 deadline will incur
hefty fines has been proved unfounded.
The Petroleum Authority of Thailand (PTT) has persistently claimed the
conservationists' protests are detrimental to the country's interests,
saying a fine of as much as 100 million baht will be imposed if gas
delivery cannot commence by July 1, 1998.
The PTT cited this reason in its previous rejection of the
conservationists' request for a public hearing which, had it been done,
would have spared pristine forest through which the pipe will run. The
laying of the gas pipeline through wild elephant and rare crab and bat
habitats has seriously disturbed the area's unique biodiversity.
On the second day of the project review hearing (Feb 15), PTT's public
relations chief Songkiert Tansamrit continued to insist that the project
delay would entail a huge cost, ranging from interest on loans to fines
from both the gas exploration consortium, of which PTTEP holds a 25 per
cent stake, and the construction contractors, altogether amounting to
US$560 million or 28,000 million baht.
On the other hand, conservationists have argued that gas delivery can be
postponed for at least 30 days, a point affirmed by a report on January
12 by a legal panel appointed by the prime minister to review the
contract. The period covers the trial delivery of gas to the Ratchaburi
power plant and the plant's run-in test. The PTT had always denied this
interpretation, however.
Eventually, on February 15, PTT confirmed the conservationists'
assertion that the date of commencement was August 1. Any penalty can
only be imposed after that date.
The second revelation came on February 18 when it became clear that the
Ratchaburi power plant, to which the Burmese gas is being delivered,
might not be finished on time. Jira Chomhimvet, an engineer in charge of
gas pipeline construction, admitted that: "We can eventually claim the
gas... once the power plant is finished and the country is ready to take
it. In the end, the only money we will lose will be the interest".
If the construction of the Ratchaburi power plant cannot be completed by
the July 1 deadline, the PTT can ask Burma to postpone gas delivery, and
have the withheld gas transferred to the following years' import. The
PTT is only committed to make the advance payment stipulated in the
contract to consortium members.
In short, the only additional expense the PTT is obliged to pay in case
of delay is the interest on the advance payment to the consortium in
accordance with the length of the postponement of the gas delivery.
An official from the Electricity Generating Authority of Thailand (Egat)
explained that the advance payment is 150-170 million baht a month, and
affirmed that the sum is not a fine. If the Ratchaburi power plant can
start generation by November 1 it means the entire project can be
postponed for three months from July 1 to October 1 (the first date of
the run-in test).
At a 12 percent interest rate (used by the PTT in calculating the 28,000
million baht damage mentioned above), the interest the PTT will have to
pay for the three-month delay will come to only 4-5 million baht.
At the moment, representatives from both Egat and the PTT are reported
to be in Yangon negotiating with the Burmese government for leniency
over the fines.
2. Another benefit of the hearing is its bringing to light information
regarding Egat's Ratchaburi powerplant project. The revelation is
significant because it exposes the inconsistency of information that
Egat and the PTT have been feeding the public.
On February 18, Sirithat Klankwamdi, Egat's assistant director for
planning and policy, admitted that the 200,000-million-baht Ratchaburi
powerplant will be completed at least one month later than scheduled due
to construction delays. However, he insisted that if the PTT remained
firm in its resolve to have the gas delivered on July 1, Egat would try
to have the first power unit ready on time.
The testimony was not in line with the view of Egat's governor Veeravat
Chalayon. A few days earlier he was quoted as saying that his
organisation was negotiating with the PTT to adjourn the delivery date.
Egat's lack of liquidation, coupled with the rising cost of
construction, was causing the delay.
Since Egat is unable to obtain a loan to pay for the first unit with
this year's budget it is assumed that the agency will postpone payment
until the budget for next year is approved (on October 1). Under the
circumstances, the plant delay is inevitable. An earliest possible test
run would be after October 1.
3. Mr Sirithat testified to the committee that the construction of the
power plant would increase the reserve electricity supply to 25 percent,
based on the current forecast of electricity demand. There are two
issues involved here: First, the Egat representative agreed that the
present reserve of electricity stands at 12 per cent, calculated by
comparing the total supply (16,233 MWs) with the peak demand for 1997
(14,506.3 MWs).
A large reserve is definitely beneficial for the nation's energy
security. But just as a trader may spend too much money hoarding goods,
we may likewise have overspent on storing electricity.
For example, an overestimation of electricity demand by a mere three
percent in 1997 resulted in Egat losing US$833 million (33,320 millions
baht - calculated at 40 baht to the dollar). Any attempt to increase
power supply, be it construction or expansion of electricity generation,
or imports of electricity, are bound to suffer from currency rate
fluctuations.
Second, the Egat official testified that the 4,600-MW power plant in
Ratchaburi was necessary to meet an annual increase in demand of power
by 10 per cent. At the same time, Egat governor Mr Veerawat confessed
that power demand will actually decline, saying it only grew by 3.2 per
cent last year.
To cut down on oil imports, Mr Veerawat also proposed that the PTT link
the gas pipelines from Ratchaburi to ones from the Gulf of Thailand,
which will serve two power plants in Southern Bangkok and Bang Pakong.
It will also solve a problem if Egat has to step down gas demand from
525 million cubic feet per day (mmcfd), as specified in the contract, to
380 mmcfd. The PTT Gas president Piti Yimprasert stated to the committee
on the last day of the meeting (Feb 18) that the PTT only wants 180
mmcfd to serve a combined cycle power plant with 1,000 MW capacity (see
below).
If that is the case, it implies that Egat is proposing to downscale the
generating capacity of the Ratchaburi power plant to only 2,000 MWs. In
other words, the plan to build thermal-power stations will be put off
for good, and Egat will have to cut by half the capacity of the
Ratchaburi plant.
4. The gas pipeline project and the Ratchaburi power plant were the
brainchild of a cabinet resolution in October 1993 which suggested that
it become the central electricity load for the Western Seaboard
development project. However, Egat later proposed that the pipelines
from Ratchaburi be linked to those from Wang Noi (Ayutthaya province), a
plan accepted by the PTT.
We conservationists demand clarifications from the PTT and Egat:
First, if Egat's Ratchaburi plant bought only 380 mmcfd from the PTT, it
would only be able to generate 2,000 MWs per day to serve the entire
Western region. All the other power stations have already been
adjourned, and are unlikely to resume in the near future in light of the
present economic circumstances. What would happen to the remaining 145
mmcfd the PTT plans to buy from Burma?
In a similar vein, the extension of the project (to incorporate the
Ayutthya plant) can be regarded as against the original cabinet
resolution, which clearly stated that the PTT is committed to obtain
sufficient natural gas to fuel the Ratchaburi power plant as soon as
possible. The requirement led to the Memorandum of Understanding which
stipulated basic conditions in trading gas between Thailand and Burma in
October 1994 and the official contract signing in February 1995.
It should be noted that both the cabinet's resolution and the MOU were
done during the first term of the Chuan Leekpai government.
Moreover, the hasty manner in changing the projects reflects a lack of
effective planning and cooperation between the two organisations. In
fact, all the projects have entailed huge expenses, shoving ever larger
burdens on the taxpayer.
Thais should be aware that the government has recently encouraged state
enterprises to obtain domestic loans with a three to 10-year term,
instead of foreign loans. This year Egat asked to postpone repayment of
its seven-billion baht loans with the Government Savings Bank, while
extending its bonds worth 22.3 million baht. Egat also opened a special
overdraft account worth three billion baht with the Krung Thai Bank and
asked the bank to issue trust receipts for imported machinery.
In the meantime, in 1996 the PTTEP raised funds for the Yadana gas
project by issuing debentures in the US worth US$200 million (or 10,000
million baht). Similar bonds worth the same amount were also issued in
Japan in 1997.
Third, if the plan to link gas pipelines from Ratchaburi to Wang Noi
materialises, the government should review the entire cost of production
of the gas. Don't forget that the calculation of the gas price must
include the cost of pipeline construction. The longer the pipelines are,
the more expensive the price per unit of gas.
The PTT repeatedly claims that Yadana gas was chosen because of its
competitive price when compared to obtaining gas from the Gulf of
Thailand or the Joint Development Area (JDA) between Thailand and
Malaysia, due to the shorter distance and lower costs of pipeline
installation.
However, an installation of the gas pipelines from Ratchaburi to Wang
Noi would mean that the pipelines from Burma to Thailand would together
be as long as 1,000 kms (300 kms from the Yadana rig to Burmese shores,
63 kms from there to Ban I-tong village, 260 kms from Ban I-tong to
Ratchaburi, and 300-kms from Ratchaburi to Wang Noi), or about the same
distance as from the JDA.
All the above reasons mean the government should revise both the
pipeline and the Ratchaburi plant projects. It has been demonstrated
that both the PTT and Egat can put off the project for at least another
three months without extra expenses.
At the same time, the Environmental Impact Assessments (EIA) of both
projects have been found to be flawed by members of the committee,
notably Dr Jiraphol Sinthunawa (Mahidol University) and Dr Suraphol
Sudara (Chulalongkorn University).
Accordingly, proposals to review the projects, citing economic and
environmental reasons, are deemed legitimate. This is on top of the
ethical questions of trading with the Burmese junta raised by
conservationists in the closing speech at the meeting.
Pibhop Dhongchai is an adviser to the Kanchanaburi Conservation Group
and its alliances and secretary-general of the Campaign for Popular
Democracy
------------------------------------------------------------------------